You would need a structural engineers report to get a building warrant to be allowed to touch that beam.

The wood beam is supported by the load bearing pillar in the middle. If you remove the centre pillar, then beam would need to be much stronger to cover the full width unsupported (probably a steel RSJ). The engineer would also have to approve the brickwork at each end (now supporting the whole lot). You would probably need a proper set of plans to submit to the Building Control Officer. Could be looking at up to £1K to get plans, structural engineers report and building warrent.

Then you need to pay for the RSJ (probably), double door and builder.